Awarding Agency
|
Agency Name and Address |
South Grafton Water District
370 Providence Road
South Grafton, MA 01560 |
Project Number |
2024-1 |
Estimated Cost |
$5,000,000 |
Contractor Qualification |
DCAMM Certificate |
Required for DCAMM contracts over $150,000, Highway Division contracts over $50,000.
|
Contact Information |
Name |
Francine Carrigan |
Phone |
508-281-5160 |
Fax |
|
Email Address |
fcarrigan@ceiengineers.com
Notify email address listed when final publish date assigned. |
Contract Information |
Project |
The work for this project generally consists of constructing a 40’ x 50’ metal building with slab on grade foundation and equipment for PFAS removal to treat 650 gallons per minute flow from nearby Wells #2 and #3. The PFAS filter vessels are a single train with two 10-foot diameter tanks using Flouro-Sorb filter media. The system will include SCADA integration, flow meters, interior piping, gauges, valves, dehumidification system, and a natural gas backup generator system. Miscellaneous site features include a lined backwash basin, infiltration basin, fencing, gravel, grading, bollards, and paving. |
Plans/Specification Available |
April 23rd at Comprehensive Environmental Inc., 41 Main Street Bolton, MA 01740. For electronic copy email request to fcarrigan@ceiengineers.com |
General Bid Deadline
|
05/29/25 |
Time |
2:00 P.M. |
Sub Bid Deadline
|
05/15/25 |
Time |
2:00 P.M. |
Sub Bid Category |
Painting, Plumbing, HVAC, Electrical |
Additional Information |
|
View the online copy of this publication.(hyperlink) |
|