Agenda

MHC’s Consultation Meeting Regarding Shea Circle Project (within the Route 203 Corridor Reconstruction, Casey Overpass Project), Boston (Jamaica Plain), MA

January 31, 2014
2:30 p.m. – 4:00 p.m.
at Massachusetts Historical Commission

  1. Introductions.
  2. Summary of MHC’s consultation process (950 CMR71) and goals of the meeting.
  3. Discussion of MassDOT’s Shea Circle Alternatives Analysis dated November 19, 2013.
  4. Exploration and consideration of project alternatives that could eliminate, minimize or mitigate the adverse effect.
  5. Summary of the meeting and next steps.